Construction schedule template: free Excel download with a Gantt chart (renovation edition)

Free Excel construction schedule template with a built-in Gantt chart: change the start date and durations and the dates update automatically. Includes 14 common renovation work items in order with typical durations, and where Excel schedules usually break down.

By the Everywhere Design team2026.10.073 min read
Contents
Download the construction schedule template (Excel) ↓No sign-up, downloads straight away | Opens in Excel, Numbers and Google Sheets

Want crews to see it on their phones?Free 30-day trial →

Before any job starts, the first thing to do is lay out the construction schedule.

This template follows the order we actually schedule work in. It’s free to download; change the start date and it’s ready to use.

Download the template

  • Change the “Start date” and the weekdays, dates and Gantt bars update across the whole sheet
  • Change the “Days” for any item and the following items move back automatically
  • If two items overlap, just edit the start date on that row

The columns a useful construction schedule needs

ColumnWhy you need it
Work itemList items in construction order; breaking them down to “one crew, one job” makes scheduling easiest
CrewWho is due on which day, so each crew can see it at a glance
Start / end dateCalculate the end date as start date + days − 1 rather than typing it, so changing one doesn’t throw everything out
DaysWhere you estimate duration; when the job slips, this is the only cell you change
Gantt chartDates drawn as bars: overlapping crews and gaps are faster to spot in a chart than in numbers

Common renovation work items and typical durations

OrderWork itemTypical days
1Site protection1
2Demolition2–4
3Plumbing and electrical rough-in3–5
4Masonry (walls, plaster, waterproofing)5–10
5Tiling4–7
6A/C pipes and ducted indoor units1–3
7Carpentry (ceilings, partitions, cabinets)10–20
8Painting (filler, primer, topcoat)6–10
9Modular cabinet installation2–4
10Flooring1–3
11Lights, switches and sockets1–2
12Curtains and wallpaper1–2
13Final cleaning1
14Inspection and snag fixes2–5

Reference figures for a mid-size home renovation in Taiwan; actual time depends on size, methods and whether the layout changes | Wall-mounted split A/C units are usually installed after painting

Two places are the easiest to get wrong.

The first is masonry and waterproofing: they need drying time, so the next crew can’t start the moment they finish.

The second is carpentry and painting: filling only starts once ceilings and cabinets are done, and together these two stages are usually the longest part of the job.

How to build a Gantt chart in Excel yourself

  • To the right of the table, add a row of date columns, one column per day: the first equals the start date, and each column after it adds 1
  • Select the Gantt area and use conditional formatting with a formula that fills the cell when the column’s date is between the row’s start and end dates
  • Add a row of weekday letters above the dates so weekends stand out

If you’d rather not build it, the template above already does this, and the Gantt bars show up in Excel, Numbers and Google Sheets.

Where Excel schedules usually break down

  • Delays: one crew runs two days late and a dozen later items all need moving, while remembering to skip weekends
  • Mismatched versions: the sheet is on the office computer, and the crews have last week’s screenshot from the group chat
  • No reports from site: to know what is really finished you phone people one by one, so the schedule is always a step behind
RelatedHow long does a renovation take? →Total duration by scope of work, and why each trade can’t be rushed

Once it’s scheduled, staff and supervisors see it on their phones

Everywhere Design is a project management app for construction and renovation teams.

The schedule is a Gantt chart. When the job slips, shift everything at once, with the option to skip weekends.

Staff and supervisors view the schedule on their phones, check in by GPS on arrival, and site photos are filed by trade under each site.

30-day free trial, no credit card required.

FAQ

Do I need project management software like MS Project to make a Gantt chart?

No.
A typical home renovation has 10 to 20 work items, which Excel handles fine. The template in this article is ready to go: download it and change the start date.

What is the difference between a baseline schedule and a working schedule?

They are similar.
A baseline schedule is usually the plan shown to the client or main contractor before work starts; a working schedule is the one you keep updating during the job and use to book crews.

How do I adjust the schedule when work is delayed?

In the template, change the days for the delayed item and everything after it moves back automatically.
If you need to shift the whole job and skip weekends, a scheduling app is much faster than editing by hand.